Residential Complex in the Neighborhood at Hochmuttinger Straße
In Munich, we are building with wood while keeping an eye on the future
Location:
Munich-Feldmoching
Client:
Münchner Wohnen Immobilien 4 GmbH
Architectural Design:
dressler mayerhofer rössler architekten und stadtplaner gmbh
Structural Design:
Mayr | Ludescher | Partner
Construction Supervision:
a + p Architekten
Assembly Partner:
L+S Baucon GmbH
Construction Period for Wooden Structures:
da maggio 2024 ad agosto 2025
Living the Future: A New Neighborhood Built in Wood
North of Munich, on an area of 8.4 hectares, a new residential space has been created to offer a high quality of life. The new complex, located on Hochmuttinger Straße, provides not only space for 161 subsidized apartments but also includes social facilities, ranging from assisted living residences to supportive shared housing.

For this project, we at Rubner handled all aspects related to wooden structures, from design to prefabrication to assembly. Four of the eight buildings are made entirely of wood, while the other four are hybrid structures with a concrete load-bearing framework and wooden facades.
Efficient Design, Impeccable Execution
The main challenge? A construction site with limited logistical space and the simultaneous construction of the raw structure. Thanks to the high degree of prefabrication, with windows already integrated and finished wooden cladding panels, we were able to deliver the elements just-in-time and assemble them in a short time. The entire process was coordinated through a digital Kanban Board system.
From an ambitious idea to a vibrant place.
A project that demonstrates how wood can play a leading role even in large-scale residential construction, in an ecological, efficient manner, and perfectly integrated into the urban context.
Overview of Our Services
- Detailed execution design and assembly
- Prefabrication and supply of all wooden elements, including windows, façade cladding, solar shading systems, and prefabricated loggias
- Assembly in collaboration with L+S Baucon GmbH
Project Data
- 161 apartments distributed across 8 buildings
- 10,774 m² of wooden frame walls
- 5,865 m² of hybrid wood-concrete floors
- Duration of the construction work for wooden structures: 14 months